Construction continues on Olsen Road California Lutheran University began installing about 2,500 feet of new water line improvements on Olsen Road between Wildwood and Morningstar avenues last week. The work, which has been contracted out to B&W Pipeline, Inc., is being carried out in the westbound lane closest to the median. Weather permitting, the work will take about seven to eight weeks to complete. Additional water line improvements will be installed at the intersection of Campus Drive and Olsen Road in late July over a three-to-four- week period. For information about the project, call Valerie Crooks at (805) 493-3287 or visit the website at www.clunet.edu. |
|||||